Renovate 2.0

Donated: $1,000,000

 

Goal: $1,000,000

 

Give NowProject Updates

Project Status

Renovate 2.0 is complete! We have reached our fundraising goal.

Pioneer- your faithfulness and generosity are inspiring and demonstrate a commitment to the health and inclusion of all our members and guests! On behalf of the Pioneer pastors and staff and the Stewardship Committee, our hearts are overflowing with gratitude.

Please consider joining us July 20 in either church service for a special celebration now that we have finished both the project and fundraising for Renovate 2.0! Thank you for your generosity to the rest of the church's mission.

Thank you, Pioneer! The best is yet to come!

Please take a look at the video below. There are some people who want to say “Thanks” personally.

A you can see in the video, the elevator is an important access point for so many parishioners and guests.

Give Now

Project Updates

January 24, 2024

Fundraising:

  • The fundraising is almost completed! The Pioneer Memorial Church members and community have demonstrated their commitment to “Love On The Move”. The sacrificial giving for this improvement is inspiring to those who are using the elevator (and the other improvements) and to the Pastoral staff and Stewardship Committee. There is only $66,984 to raise! Thank you so much! Let us press forward to complete Renovate 2.0!

September 27, 2023

The Project:

  • Have you tried the new elevator yet? It is complete and the glass door is installed. Many seniors and others with a need for transportation between floors are now able to reach the sanctuary and the lower level. What a blessing!

Fundraising:

  • Will you help us reach the goal of having it fully paid for by December of this year? We are over ¾ of the way there. See our temperature gauge in the lobby to see the weekly progress on the last quarter. We can make this happen! Please help pray for the completion of our Fundraising goal. As of 9/23/23, there is $770,105 that has been raised with $229,895 to reach our goal!

September 15, 2023

The Project:

  • The elevator is completed and operational! All those who have needed this addition are welcome to use it.
  • Next, the glass wall will be installed, and the project will be done!

Fundraising:

  • As of 9/2/23, there is $751,570.00 that’s been raised with $249,430.00 left to go.
  • We are so close!- Please join with others to finish this wonderful addition!
  • Remember Renovate 2.0 in your giving plans and pray for its completion!

May 27, 2023

The Project:

  • It’s nearly done! Essentially, the only major piece of the Renovate 2.0 left to complete is the arrival and installation of the elevator itself.
  • After the installation is the final finishing painting and flooring and it's ready for use!!!

Fundraising:

  • As of 5/13/23, there is $660,509.00 that’s been raised with $339,491.00 left to go. We are making wonderful progress. Thank You!
  • Please remember Renovate 2.0 in your giving plans and pray for its success!

May 6, 2023

The Project:

  • The elevator shaft is built. The new stairs are installed.
  • The last drywall should be hung next week.
  • Cabinets and carpet will start being installed very soon.

Fundraising:

  • As of 4/22/23, there is $593,701 that's been given. Thank You!
  • Please remember Renovate 2.0 in your giving plans and pray for its success!

April 29, 2023

Video Update:


April 1, 2023

The Project:

  • The foundation for the elevator is poured. The entrance to the elevator waiting area is open but not finished.
  • The new offices for the media team are painted. It’s getting done!

Fundraising:

  • As of this March 28, you have generously contributed $570,566. Thank-you!
  • Please remember Renovate 2.0 in your giving plans and pray for its success!

February 18, 2023

The Project:

  • Part of the floor in the music room is excavated and the new concrete foundation support for the elevator began with the pouring of the concrete starting on 2/7.
  • New walls for the expanded Media Ministry offices, temporary walls equipment and material storage, various utility rerouting around the new elevator.

Fundraising:

  • As of this week, you have generously contributed $515,272. Thank-you!

December 21, 2022

The Project:

  • Construction begins on Tuesday, December 27.
  • All church entrances will remain open for Sabbath services; however, the only entrance to the Youth Chapel will be the outside entrance closest to the Wellness Center.
  • The small elevator at the awning entrance will not be in use starting December 27.

Fundraising:

  • As of this week, you have generously contributed $309,738 including the second portion of a $100,000 matching grant. Thank-you!

November 30, 2022 

The Project:

  • The final guaranteed cost, as submitted by the general contractor, Weigand Construction, is $929,641.
  • This amount includes a 3% contingency. The project begins on Tuesday, December 27, and is to keep on-budget.
  • The elevator is on order and should be here mid-May 2023.

Fundraising:

  • As of this week $225,627 that have been raised. This amount includes one portion of a $100,000 matching grant.