  • The Project: Part of the floor in the music room is excavated and the new concrete foundation support for the elevator began with the pouring of the concrete starting on 2/7;
  • in progress: new walls for the expanded Media Ministry offices, temporary walls equipment and material storage, various utility rerouting around the new elevator.
  • Fundraising: As of 2/12/23, there is $515, 272.00 that’s been given. Thank You! This amount includes the third and final portion of the $100,00 matching donation.